MBTA – North Side ATC Implementation 

MBTA – North Side ATC Implementation 

The MBTA awarded a project to Hitachi Rail STS to design and implement a federally mandated signal control system to enhance safe rail operations. 

Bison Rail was hired by Hitachi Rail STS to manage and execute the Testing and Commissioning portion of the project. Bison was responsible for the management of all day-to-day activities regarding testing and commissioning. Qualified signal personnel performed post-installation verification checks, signal system pre-testing, wayside device validation and technical support during the system cut over.  

As part of the testing and commissioning process the following activities were completed.  

Location

Boston, MA

Client

MBTA

Services

  • Design mark-ups 

  • Rack to Rack wiring 

  • Cable Testing & Validation 

  • Signal bungalow wiring 

  • Wayside equipment wiring (switch machines & signals) 

  • Signaling Testing 

  • Wire tagging 

  • Point checking 

  • Microprocessor configuring and testing: Microlok, Electrologix & XP4s 

  • Cutover support 

  • Troubleshooting 

Bison Rail Systems

63 Main St. 

Suite 204

Flemington, NJ 08822

Telephone: 908-642-4570

Email: BRSadmin@bisonrailsystems.net 

Bison Rail Systems is the provider of technical services that your organization needs to help your project succeed.
Bison is a value‐added MBE/DBE/SBE partner 

bottom of page